2023 City-Wide Asphalt Overlay (P2301)

Project Description

This project is for HMA improvements for the following streets: 

  • W. Canal Dr. (N. Columbia Center Blvd. to N. Kellogg St.) 
  • W. 10th Ave. (S. Union St to US-395) 

Work will involve planing (grinding) as called for on the plans, HMA overlay, patching of miscellaneous failed areas, concrete sidewalk ramp upgrades, pavement lane striping, cross walks, stop bars, markings, cast-in-place traffic curbing and other related work, all in accordance with the attached contract Plans, these Contract Provisions, the City of Kennewick Standards and Specifications, the Washington State Department of Transportation Standards and Specifications, and in compliance with the Americans with Disabilities Act. 

More Info

Start Date:
June 2023
Est. End Date:
Spring 2024
Funding Source:
Arterial Street Fund

Click here to view the updated project flyer! (May 2021)

Contact Info

Contractor: Granite Construction Company - Ryan Engel, Project Manager (509)221-8839

City of Kennewick Project Engineer: Kendrick Glover (509)585-4464

Status

***Contract is currently suspended***

Double yellow line removal and replace will take place in spring 2024.  

Last updated 1/29/2024