Clearwater Ave. Overlay - Ridgeline Dr. to Steptoe St.
Clearwater Ave. Overlay - Ridgeline Dr. to Steptoe St.
Project Description
This project is for HMA improvements for Clearwater Ave. from Ridgeline Drive to Steptoe St. intersection. Work will involve planing (grinding), HMA overlay, patching of miscellaneous failed areas, concrete sidewalk ramp upgrades, pavement lane striping, cross walks, stop bars, markings, cast-in-place traffic curbing and other related work. Certain components of this work shall be completed at night to minimize disruptions to traffic.
More Info
Start Date:
July 18, 2022
Est. End Date:
Late September 2022
Funding Source:
Arterial Streets Fund & ARPA Federal Funds
Project Contacts
City Project Engineer: Mohammad Jalalyar, P.E. - (509) 585-4430
City Project Inspector: Steve Rountree - (509) 222-0352