Garfield/Blackberry Canyon Storm (P2019-21)

Project Description

Project will pipe the storm outfall flows from Blackberry Canyon to Park Hills Drive, eventually flowing into the Frog Pond off 10th Ave. This pipes the west side ditch along Garfield. The purpose of the project is to decrease the time-consuming yearly maintenance it takes City crews to complete on this open-ditch.

More Info

Start Date:
September 2021
Est. End Date:
TBD
Funding Source:
General Storm Fund

Project Contacts:

City Project Engineer: Kendrick Glover, P.E., - (509) 585-4464

City Project Inspector: Steve Rountree - (509) 222-0352

Contractor: Allstar Construction Group, Inc. - (509) 943-9825

Status

The contractor is installing pipe and manhole structures along the side of the road between W. Park Hills Drive and W. 19th Ave. 

Please be aware of construction vehicles working in the area and expect delays.

Last updated 6/20/2022