2021 City Wide BST (P2021-21)

Project Description

This project consists of the application of bituminous surface treatment (BST) seal coat of paved arterial streets within the Kennewick City limits. A quickset fog seal will be applied following the post-BST application.

More Info

Start Date:
June 7, 2021
Est. End Date:
July 23, 2021
Est. Cost:
$560,000
Funding Source:
Local Pavement Preservation fund


BST

Status

Contract was awarded in December with plans to start construction no earlier than June 7, 2021.

Last updated 2/24/2021