Zone 2 W. 7th Ave Transmission Main (P1912-19)

Project Description

This Capital Improvement Project involves the installation of a 30-inch diameter ductile iron transmission main pipe from W. 10th Ave and S. Edison St. intersection along Edison St. to W. 7th Ave, then along W. 7th Ave to a private access road and utility easement, then along the private access road to W. 4th Ave. The Project also includes the installation of a 16-inch diameter ductile iron transmission main pipe from W. 10th Ave and S. Edison St. intersection along W. 10th Ave. to S. Dawes St.

Important Dates

Start Date:
February 2020
Estimated End Date:
September 2020
Funding Source:
Water and Sewer Fund
Estimated Cost:
$2.7 million

Contacts

P1912 contacts

Status

Awarded and expecting to begin construction in February.

Last updated 1/22/2020