Zone 2 W. 7th Ave Transmission Main

Project Description

This project will extend a 30-inch water transmission main from 4th & US395 to 10th Ave & Edison. The new transmission main will do the following; increase flow capacity conveyance from the Golf Course pumps station to 18th & Kellogg, reduce pump station discharge pressures, and increase reliability within zone 2.

Important Dates

Start Date:
February 2020
Estimated End Date:
September 2020
Funding Source:
Water and Sewer Fund
Estimated Cost:
$2.7 million

Status

Scheduled to be awarded on January 21, 2020 to Tapani, Inc.

Last updated 1/16/20