UPRR 24-Inch Sewer Interceptor Phase 2

Project Description

This project is for the construction of the UPRR 24-lnch Interceptor Sewer Rehabilitation Project and consists of rehabilitating the UPRR 24-lnch Interceptor Sewer. The rehabilitation effort includes approximately 2,404 linear feet using trenchless rehabilitation techniques (CIPP thermally cured or UV cured) and 548 linear feet of new open cut 8-inch sewer forcemain pipe. The project also includes a 24-inch diameter boring and jacking below the Union Pacific Railroad.

Important Dates

Bids must be turned in by June 27, 2019 at 2:00 P.M. at 1010 E. Chemical Drive in Kennewick.

Status

This project is currently out for bids. To see more information please visit our Bid Opportunities page.

Last updated 6/17/19