Street Waste Facilities (P1607-18)

Project Description

This project consists of the construction of a street waste facility.  Works includes, but is not necessarily limited to, installation of storm drainage, water and sewer lines, street sweeper and vactor stations, clarifier, waste storage facilities, asphalt concrete pavement, irrigation, landscaping and other related work.

Important Dates

Start Date:
January, 2019
Estimated End Date:
June, 2019
Location:
Northwest Corner of W. 10th Avenue and Steptoe Street
Estimated Cost:
$ 868,000

Status

Installed main gate with fencing and landscaping under way.

Last updated 5/30/2019