UPRR 24-inch Sewer Interceptor

Important Dates

Start Date:Late December, Early January
End Date:April, 2019
Location:Union Pacific RR tracks, east of Edison Street
Estimated Cost:$836,000


Project Description

This project is for the construction of the UPRR 24-inch Interceptor Sewer Rehabilitation project parallel to the Union Pacific Railroad. The project consists of rehabilitation of approximately 3,200 lineal feet of 24-inch diameter RCP sewer utilizing trenchless technology, cured-in-place pipe (CIPP). All manholes will be sprayed with a protective lining to reduce hydrogen sulfide induced corrosion.

Status

Rotschy, Inc will be awarded this contract at the November 20th City Council meeting. The preconstruction meeting will be scheduled for late December.